Subscribe to Our Weekly Newsletter
Agencies

Texas Regulators Merge Two Permian Power-Line Cases on the Question of Need and Decide Neither

Texas Regulators Merge Two Permian Power-Line Cases on the Question of Need and Decide Neither

The Public Utility Commission of Texas called a special meeting Aug. 21 for the sole purpose of taking up two of the giant power lines proposed to carry electricity out of the Permian Basin, moved it into a hotel ballroom to hold the crowd, heard argument from the parties, and then approved nothing, denied nothing and paused nothing.

What it did instead was procedural, and it may matter more than a vote would have. In two orders signed that afternoon, the commission unabated the older of the two cases — restarted a docket it had frozen in June — and then consolidated both cases on a single issue: whether the lines are needed at all.

“It is therefore ordered that Docket No. 59029 and Docket No. 59315 are consolidated on the issue of need for the transmission lines and associated facilities,” the order reads. “Evidence related to the issue of need that has been admitted in either docket is deemed admitted in the consolidated proceeding.”

Newsletter

Latest News, Direct To Your Inbox

Get the most important Texas news and conversations delivered to your inbox.

Both cases are back on the agenda Aug. 28, one week later, alongside a third 765-kilovolt application the commission had not previously posted.

The two dockets are Oncor Electric Delivery’s applications to build the two halves of what the commission calls Import Path 1: Docket 59029, the Longshore Switch–Drill Hole Switch line, roughly 160 miles across 10 West Texas counties, and Docket 59315, the Dinosaur Switch–Longshore Switch line, 235 to 270 miles across 22 more. Together they reach 30 distinct counties. They meet at the Longshore Switch, a yard of high-voltage breakers about 4.5 miles west of Forsan in Howard County — and that shared endpoint is the whole legal basis for what the commission did.

The commission also lifted its own freeze on the western case. It had abated Docket 59029 on June 17 because the eastern case was still at the State Office of Administrative Hearings; the Aug. 21 order states that “[b]ecause Docket 59315 has been remanded to the Commission, the Commission unabates this proceeding for continued processing of this case.” A state administrative law judge had recommended back on May 12 that the commission grant the Longshore–Drill Hole application and approve route 476. That recommendation has been sitting unacted on for more than three months.

The timing around the meeting is the part worth holding onto. The morning it convened, 31 members of the Texas House filed a statement in these dockets asking the commission to deny all five pending 765-kV applications and leave the permitting process to the Legislature to rewrite. It was time-stamped 8:53 a.m., roughly four and a half hours before the two orders issued. The day before, state administrative law judges had recommended that the commission deny a different pair of 765-kV lines outright — finding that need had not been proven and that notice to some 1,400 landowners was defective.

Read against that, consolidating the two Oncor cases on need is a consequential housekeeping act. It means the commission will not decide whether the Permian needs the western leg and separately whether it needs the eastern leg. It will decide the need question once, on a record pooled from both proceedings, for a 400-mile system across 30 counties — at the same moment that need is the ground on which a sister project was just recommended for denial.

Two motions that were pending going in appear to be pending still. American Stewards of Liberty, a Georgetown-based property-rights group that is an intervenor in both cases, moved Aug. 11 to abate them; the utilities opposed the motion Aug. 18 and the group filed a reply the morning of the meeting. No written order granting or denying that motion exists in either docket. The Aug. 21 unabating order is a different animal entirely — it lifts the commission’s own June freeze on Docket 59029, not the group’s request.

A landowner in the eastern case, Garland Richards, had asked Aug. 12 for oral argument at the Aug. 28 meeting. There is no order on that motion either. The commission simply noticed argument for Aug. 21 instead — a week earlier than he asked.

The commission’s options narrowed on Aug. 21 rather than widening. Its next meeting, Aug. 28, now carries three 765-kV cases: the two Oncor lines consolidated on need, and Docket 59336, the AEP Texas and CPS Energy Howard-to-Solstice line across 14 counties, which was not on either August special-meeting agenda and which the Dispatch has reported faces an Aug. 31 statutory decision deadline. The two dockets recommended for denial the day before — 59475 and 59182 — do not appear on the Aug. 28 agenda at all yet.


Fact Box

When
Special open meeting: Friday, Aug. 21, 2026, 9:30 a.m. CT, AT&T Hotel and Conference Center. Orders filed 1:22 and 1:23 p.m. Next regular open meeting: Friday, Aug. 28, 2026, 9:30 a.m., Stephen F. Austin Building, Room 170, 1700 Congress Ave.

Archived video
PUCT Open Meeting, Aug. 21, 2026, AdminMonitor. Video only


Newsletter

Latest News, Direct To Your Inbox

Get the most important Texas news and conversations delivered to your inbox.