Families who buy the last 196 homes at Riverbend at Double Eagle, a Meritage Homes subdivision in unincorporated Bastrop County, would pay an estimated $2,983.84 a year on top of their property taxes to repay the cost of the subdivision’s public improvements, including a bridge, according to a preliminary bond offering document posted with the Bastrop County Commissioners Court’s Nov. 23 agenda. The court scheduled a vote that day to approve the proposed assessments and call a public hearing on them for Dec. 14.
The payments are assessments in the Double Eagle Ranch Public Improvement District, a special district that lets the county borrow for a developer’s public improvements and repay the debt from charges on the lots that benefit. Under the plan, each of the 196 lots in the district’s third and final phase would carry a maximum assessment of $33,091.84, or $6,486,000 in all.
The offering document puts the yearly cost in tax terms. The estimated average installment equals about 78 cents per $100 of a home’s value. The overlapping property tax rate in the area for 2027 is $1.72277 per $100: Bastrop County, its special road tax, Bastrop ISD and two emergency services districts. Together, the document says, a homeowner’s combined rate would be about $2.51 per $100.
For a buyer, the document estimates a finished home’s value at $380,500. At that value, the property taxes would come to roughly $6,555 a year before exemptions, and the assessment would add about $2,984, a Dispatch calculation from the document’s rates. The offering document says the assessment figures are preliminary and subject to change.
The development, about 196 acres off Double Eagle Ranch Drive, sits in Bastrop County and in the extraterritorial jurisdiction of the City of Bastrop — the unincorporated land outside a city’s limits where the city has only limited powers — about 20 miles southeast of Austin, according to the document. It is a county project because the land is outside any city. Chapter 372 of the Local Government Code lets a county, like a city, create such a district and levy assessments for improvements that specially benefit the property.
The arrangement shifts who pays for growth. The county’s general taxpayers do not back the bonds. The bonds are special obligations “payable solely from” the assessments, the document says. The developer recovers its spending through the bond sale. Meritage had spent about $7.92 million on the third phase’s improvements and its water and wastewater lines as of Sept. 29, 2026, including about $2.70 million on the water and wastewater work, which is owned by the private utility Corix and not financed through the district, according to the document. Meritage separately paid about $2.9 million for an amenity center without reimbursement.
The phase is the last of three. The district’s first two phases have 105 and 181 lots, financed by earlier bonds of $3,151,000 and $6,540,000, of which $2,983,000 and $6,436,000 were outstanding Nov. 1, the document says.
Future residents will not be in the room for the Dec. 14 hearing. Statutory notice goes to “the owners of the property to be assessed,” the document says, so families who close on homes later will not receive it. Buyers learn of the charge another way: Texas law requires a seller to give written notice of public improvement district assessments before a purchase contract is signed, and a buyer who does not get it may terminate the contract, the document says.
The Dispatch has reported on Bastrop County’s limited land-use power, including its request for a state public meeting on a gas plant it cannot zone.
At the Dec. 14 hearing, the commissioners court must hear objections and may change any parcel’s assessment before it votes on an order levying the charges, after which the county can sell the bonds.
Key facts
- Bastrop County Commissioners Court’s Nov. 23, 2026 agenda includes approval of a preliminary assessment plan for Improvement Area #3 of the Double Eagle Ranch Public Improvement District and a call for a Dec. 14, 2026 public hearing (county agenda).
- 196 lots, maximum assessment $33,091.84 per lot, $6,486,000 total (preliminary limited offering memorandum).
- Estimated average annual installment $2,983.84 per lot, equal to $0.78419 per $100 of value; combined rate with 2027 overlapping taxes $2.50696 (preliminary limited offering memorandum).
- The developer is Meritage Homes of Texas, LLC; the bonds are payable only from assessments, not county taxes (preliminary limited offering memorandum).