Data-center developers have until Dec. 4 to tell ERCOT whether it may publish what they told the state about their projects, including where they are, how much power they want and how much water they will use. Projects whose developers do not sign off stay confidential.
ERCOT, the nonprofit that operates the grid for most of Texas, set the deadline in a Nov. 20 market notice to the 465 proposed data centers it surveyed in September. The survey, which went to every project of 25 megawatts or more seeking a grid connection, followed Gov. Greg Abbott’s Aug. 3 letter directing ERCOT and the Public Utility Commission to gather information on data centers’ tax breaks, grid dependence, on-site generation, water, cooling, noise and ownership.
The answers are in. In a Nov. 5 summary to the PUC, ERCOT reported that 433 projects responded, including all 245 of 75 megawatts or more, together requesting about 177 gigawatts of grid capacity. Thirty-three want more than a gigawatt each. West Texas accounts for 41 percent of the requested capacity, about 73 gigawatts.
Whether the public sees any of it project by project is now up to the companies. ERCOT’s notice says the responses are “regarded as confidential and not subject to disclosure except as may be permitted by law,” and that it “does not intend to publicly disclose this information for any given data center project unless it receives written authorization from the developer.” Each developer’s registered contact received an authorization form Nov. 20; it must come back from that same registered address by Dec. 4. The notice sets no consequence for declining.
What a developer can authorize is a fixed list of 23 survey answers: the project and developer names, latitude and longitude, owners, peak power requested, year-by-year demand and requested start date; whether the project will build on-site or backup generation, and its fuel, size and commissioning date; projected annual water withdrawal and consumption at full build-out, the share from each source, and wastewater volume and destination; construction and permanent job counts, land area, construction dates and expected noise levels. The survey’s questions on tax breaks and cooling technology are not on the list and remain confidential regardless.
Those are the questions county officials and neighbors have been asking as large projects arrive in rural and edge-of-metro counties with little public information. The Dispatch has reported that ERCOT’s separate audit of the data-center queue protects ratepayers but answers few of those questions, and that bills filed for the session would require disclosure: a public state registry of data-center water use and conditions tying grid access and tax breaks to low-water cooling. The ERCOT process asks for disclosure; those bills would mandate it.
ERCOT will report how many developers agreed in its Dec. 10 Data Center State and Community Impact report to the PUC. It will then compile the authorized information, file it with the PUC, post it on its website and announce the posting in another market notice. The Dec. 10 count will be the first measure of how much of the survey the public will ever see.
Key facts
- ERCOT market notice M-B112026-01 (Nov. 20, 2026) lets data-center developers authorize public release of 23 specified survey answers; without a signed form, a project’s answers stay confidential (ERCOT).
- Authorization forms are due Dec. 4, 2026, from the project’s registered contact email (ERCOT).
- 433 of 465 surveyed projects responded, including all 245 of 75 MW or more, requesting about 177 GW; West Texas accounts for 41 percent (ERCOT summary to the PUC, Nov. 5, 2026).
- ERCOT’s Dec. 10 report to the PUC will state how many developers agreed (ERCOT).
- The survey followed Gov. Abbott’s Aug. 3, 2026 letter to ERCOT and the PUC (ERCOT RFI page).